Skip to content
Single stream tailings – fabrication & installation works

Single stream tailings – fabrication & installation works

Delivered Iluka Resources' dual-to-single-stream tailings conversion at the Jacinth-Ambrosia mine in 5 months — complex multi-discipline fabrication, poly welding, and mechanical/E&I works across the WCP, executed safely and within schedule.

  • Supply of expansion bellows, Polyurethane spacers, bolts, nuts and gaskets
  • Development of fabrication drawings from plant isometric drawings
  • Supply and fabrication and hydro-testing of 38 rubber-lined and coated carbon steel piping spools and custom reducers)
  • Supply of HDPE pipework and fittings
  • Poly Welding (T630 Poly Welder) and installation of felid piping (400, 450 and 500mm)
  • Pencil tank piping tie in during shutdown
  • Installation of new pipework / valves and flow meters
  • Mechanical
  • Supply, welding and installation of HDPE Pipework and supports throughout WCP
  • Installation of fabricated carbon steel pipework, including pipe supports
  • Electrical and Instrumentation
  • Disconnection, dismantle, installation and reconnection of flow, density and pressure transmitters and gauges and reconnection of Warman Pump power cables

Skills/services demonstrated

  • Custom fabrication with QA — 38 rubber-lined and coated carbon steel piping spools and custom reducers, fabricated and hydro-tested in-house
  • Drawing development — fabrication drawings produced directly from plant isometrics, not supplied ready-made
  • Multi-material field piping — poly welding (T630) across 400–500mm HDPE lines alongside coated carbon steel installation
  • Shutdown-window execution — critical tie-in work (pencil tank piping) scheduled and delivered within a live shutdown, showing capability to work to a fixed outage window
  • Cross-discipline delivery in one scope — mechanical (pipework, supports) and electrical/instrumentation (transmitters, gauges, Warman pump power reconnection) handled as a single integrated project rather than separate contracts
  • Brownfield plant modification — reconfiguring an operating WCP’s piping and instrumentation to support a changed process methodology, not new-build work