HONEYMOON - WELLFIELD SMP PROJECT
Client: Boss Energy
Services: Project management, Engineering
Location: Honeymoon Uranium Project, SA
Period: July 2023

The Project, owned by Boss Energy Limited, is located approximately 80kms from the town of Broken Hill, near the South Australia/New South Wales border.

DETAILS

The scope of work comprises the provision of all labour, materials, equipment, work and services necessary to carry out the design, supply, manufacture, assembly, quality assurance, inspection, testing, packaging and identification of the Wellfields and general site construction for the Honeymoon Project in South Australia.

Access to the Project is via the Barrier Highway to the Mulyungarie Road turn off, approximately 7 kms west of Cockburn and then via an unsealed access road to the site.

SCOPE OF WORK

The initial works comprise electrical and hydro testing of 3 existing wellhouses and filter skids and refurbishment. This is followed by construction of 3 new wellfields comprising installation of pumps, installation of hdpe pipework, plumbing and electrical connections, testing and commissioning.

Task A: Develop, QA/QC, Inspection and Test Program and Work Packages

Task B: Engineering Design

Task C: Procurement, onboarding, inductions

Task D: Wellfield 1 Refurbishment and construction

Task D1: Wellfield 1 Hydro testing existing pipe, flanges valves, filter skid and wellhouse

Task D2: WF1 Refurbish filter skid and wellhouse

Task D3: WF1 Integrity test Wells

Task D4: WF1 Install pipework, pressure test.

Task D5: WF1 Install pumps, run electrical connections, test electrical.

Task D6: WF1 Commissioning; test pumps, instrumentation and pipework.

Task D: Wellfield 2 Refurbishment and construction

Task D1: Wellfield 2 Hydro testing existing pipe, flanges valves, filter skid and wellhouse

Task D2: WF2 Refurbish filter skid and wellhouse

Task D3: WF2 Integrity test Wells using Boss Integrity test plant

Task D4: WF2 Install pipework, pressure test.

Task D5: WF2 Install pumps, run electrical connections, test electrical.

Task D6: WF2 Commissioning; test pumps, instrumentation and pipework.

Task D: Wellfield 3 Refurbishment and construction

Task D1: Wellfield 3 Hydro testing existing pipe, flanges valves, filter skid and wellhouse

Task D2: WF3 Refurbish filter skid and wellhouse

Task D3: WF3 Integrity test Wells using Boss Integrity test plant

Task D4: WF3 Install pipework, pressure test.

Task D5: WF3 Install pumps, run electrical connections, test electrical.

Task D6: WF3 Commissioning; test pumps, instrumentation and pipework.

Other works included:

  • Plant demolition to remove existing steel work, solvent extraction columns and mixer settler tanks.
  • Removal of existing dryer
  • Installation of new Ion Exchange columns
  • Installation of new dryer/calciner
  • Additional SMP works to integrate the new components into the plant.
  • Upgrade and refurbishment of site amenities including offices, change and laundry facilities.