CR12 LOCKER SUPPLY
Client: BHP
Services: Project management, Engineering
Location: Olympic Dam, SA
Period: May 2019 - November 2019

The underground operational expansion taking place at Olympic Dam by BHP required the procurement of a new 600 staff changeroom facility.

DETAILS

D&S Resources were engaged to supply all ancillary equipment for the changerooms inclusive of over 600 staff lockers, recycled material bench seats, fixtures and fittings. This was supplied over a 6-month period in two stages to allow for ease of delivery to the BHP site due to the large space required for storage.

SCOPE OF WORK

Work with BHP personnel to deliver mine changeroom CR12.

The project included:

  • Designing and drafting
  • Manufacturing
  • Powder coating
  • Supply levelling feet with floor fixing holes for locker stands
  • Palatalise and package to eliminate manual handling at the delivery point
  • Organise transport and delivery